What Burlington Hydro actually does (and why your bill says "Burlington Hydro" at the top)

Ontario's electricity market is structured very differently from Alberta's, and a municipal LDC like Burlington Hydro is the clearest example of why. Burlington Hydro wears two hats at once: it is the distributor that owns the poles, transformers, substations and smart meters across the City of Burlington, AND it is your default supplier under Ontario's Standard Supply Service (SSS) rules. The bill that arrives at your home covers both jobs, and on top of that it also collects the water charge on behalf of Halton Region.

The per-kWh rate Burlington Hydro charges most residential and small-business customers is set by the Ontario Energy Board (OEB) twice a year in its Regulated Price Plan (RPP), with three structures to choose from: Time-of-Use, Tiered or Ultra-Low Overnight. Long-term fixed-rate retailer contracts exist but are a niche market in Ontario, and signing one does not change the delivery, regulatory or Global Adjustment lines on your bill, only the commodity portion. The wires that bring electricity to your Burlington address belong to Burlington Hydro regardless.

The wires + the default supply
Burlington Hydro (both roles)
  • Owns 1,600 km of distribution line and 32 substations
  • Restores power after outages (24/7 dispatch)
  • Sends the monthly bill at the OEB's RPP rate
  • Also collects the water charge on behalf of Halton Region
Alternative: licensed retailer
Long-term fixed-rate contract
  • Replaces the commodity portion of the bill only
  • Door-to-door sales banned (ECPA 2010)
  • Delivery + Global Adjustment + regulatory unchanged
  • Burlington Hydro still owns the wires and meter
A Burlington-specific quirk worth knowing

Your Burlington Hydro invoice is bi-monthly, not monthly, and it includes a separate line for water billed on behalf of Halton Region. If your bill seems higher than expected, check whether you're comparing one month against a two-month cycle. The electricity portion alone is still on the standard OEB tariff.

Where Burlington Hydro delivers power

In plain words: if you live or run a business inside the City of Burlington, Burlington Hydro is your distributor. The boundary follows the City of Burlington's municipal limits exactly, from Aldershot in the west to the Oakville border in the east, and from Lake Ontario north into the rural areas above Dundas Street.

Burlington
Service area
City of Burlington
68,500
Customer accounts
Residential + commercial
1,600 km
Distribution line
Plus 32 substations
OEB
Regulator
Standard IRM framework
Covered by Burlington Hydro
  • •Downtown Burlington and the lakefront
  • •Aldershot, Tyandaga, Headon Forest, Millcroft, Alton Village
  • •Rural Burlington above Dundas Street (Lowville, Mount Nemo)
  • •Every residential, commercial and industrial address inside the City of Burlington boundary
NOT covered (use these instead)
Communities inside Burlington Hydro's territory
Downtown Burlington Aldershot Tyandaga Headon Forest Millcroft Alton Village

Not sure which one applies to your address? Check your most recent electricity bill: the distributor's name and OEB licence number are printed at the top of the first page.

How Burlington Hydro's charges appear on your bill

An Ontario electricity bill is broken into a handful of distinct line items, all of which appear on the same Burlington Hydro invoice (plus a water section billed for Halton Region). Unlike Alberta, where the commodity is billed separately by your retailer, in Ontario almost every household sees a single integrated bill where Burlington Hydro acts as both the wires company and the OEB-default supplier.

Electricity (commodity)

The per-kWh rate set by the OEB twice a year in the Regulated Price Plan. You pick one of three structures: Time-of-Use (peak/mid/off-peak), Tiered (low- and high-block) or Ultra-Low Overnight (for EV owners).

Global Adjustment

Funds the difference between the market price and the long-term contracts the IESO signed for nuclear, hydro, wind, solar and conservation. RPP customers see this rolled into the commodity rate; bigger customers see it as its own line.

Delivery

The cost of moving electricity from the IESO-controlled grid through Burlington Hydro's wires to your meter. Includes a fixed monthly service charge plus a per-kWh distribution rate set by the OEB.

Regulatory charges

Small line covering OEB programs, the Wholesale Market Service Rate and a few other system-wide charges. Set by the OEB and applied uniformly across Ontario LDCs.

Ontario Electricity Rebate (OER)

A provincial credit that reduces the pre-tax subtotal by a percentage set by the government (currently around 13 %). Applied automatically to eligible residential, farm and small-business accounts.

HST

The 13 % federal-provincial sales tax applied to the post-rebate subtotal. Cannot be avoided; appears at the bottom of the bill.

Burlington Hydro's delivery rate is set by the OEB under the standard incentive rate-setting framework, with periodic rate applications filed publicly on the OEB's eFiling portal. The framework caps year-over-year increases against inflation and productivity targets, with limited "capital tracker" top-ups for specific approved projects such as substation renewal and feeder undergrounding.

A practical implication: if a licensed retailer offers a low fixed per-kWh rate, you'll still pay the same Burlington Hydro delivery and regulatory charges, the same Global Adjustment, the same HST. Switching retailers changes the commodity portion of your bill; switching never changes Burlington Hydro's portion.

Time-of-Use (TOU)

Peak (4-7pm), mid-peak, off-peak. Best for households that can shift heavy use to evenings and weekends.

Tiered

A low block for the first ~600 kWh per month (residential), a higher block above. Best for steady, modest users.

Ultra-Low Overnight (ULO)

Very cheap from 11pm to 7am, much more expensive 4-9pm. Best for EV owners or anyone who can charge overnight.

Contact details: outage line + customer service

Burlington Hydro uses two distinct phone numbers: a dedicated 24/7 outage reporting line, and a separate business-hours number for billing, moves, account changes and new connections.

Mailing & HQ address

1340 Brant Street
Burlington, ON L7R 3Z7

Engineering support

Available via the contact form for connections, layouts and inspections

Online portal

My Account at burlingtonhydro.com

For non-urgent questions you can also use Burlington Hydro's online tools: the live outage portal and the My Account portal at https://www.burlingtonhydro.com.

Report a power outage

If your power is out, the fastest path is to call 1-877-310-4937 (24/7) or report it on the outage portal. Live restoration estimates, cause and impacted-customer counts are published on the portal and updated during major events.

How it works: from your call to power back on
1
You report it

Call 1-877-310-4937 or use the outage portal. Have your address and account number ready.

2
Dispatch confirms

The system pinpoints the affected feeder, substation or transformer and assigns the appropriate Burlington Hydro crew.

3
Crew restores

Estimated restoration time appears on the live outage portal. Single faults: usually minutes to under an hour. Storm-wide events: longer.

4
Service back

Power is verified at the smart meter. Reset clocks, check freezer contents, and report any damage right away via Burlington Hydro's claims form.

Burlington Hydro reports its reliability performance to the OEB every year in its public scorecard, with headline metrics SAIDI (average hours a customer was off per year) and SAIFI (average interruptions per customer per year). Burlington Hydro received the 2024 Customer Service Excellence Award at the EDA Awards Gala, an industry-wide recognition of its customer-service track record.

Planned outages for maintenance are normally posted at least 48 hours in advance, by mail or notice to affected addresses and on the outage portal. If you depend on medical equipment, register with Burlington Hydro's medical-needs program so you receive priority notification.

New connection or service upgrade

For a new build, a service upgrade (e.g. moving from 100 A to 200 A for an EV charger or heat pump), a temporary construction service, or any work that requires changes to the physical wires or meter, you deal with Burlington Hydro. Start at https://www.burlingtonhydro.com or call 905-332-1851. The engineering team handles new builds, layout reviews and capacity assessments.

What you'll need before applying
1
Site address

The civic address and the legal description of the lot inside the City of Burlington.

2
Site plan

A sketch showing where you want the meter, service entrance, and run-back to the pole or underground vault.

3
Service size

The amperage (100 A, 200 A, 400 A…) and voltage you need, signed off by your Master Electrician.

4
ESA permit + certification

An Electrical Safety Authority permit and ESA sign-off once the in-house wiring is done. Burlington Hydro cannot energise until ESA clears it.

Lead time
5 business days (standard)

For routine residential connections once all conditions are met. Complex builds or service upgrades requiring civil work can run several months.

Fees
OEB-approved tariff

Fixed component + per-metre charge above the contribution threshold defined in Burlington Hydro's Conditions of Service.

Once the wires are in, your account opens automatically under Standard Supply Service at the OEB's Regulated Price Plan rate. You can switch your RPP structure (Time-of-Use, Tiered or Ultra-Low Overnight) at any time by contacting Burlington Hydro. If you sign with a licensed retailer later, the retailer registers their contract with Burlington Hydro and the commodity rate is replaced on your next bill cycle.

Moving home, transferring or closing a service

In Burlington the move-in / move-out conversation starts with Burlington Hydro directly, not with a separate retailer. Because Burlington Hydro is the default supplier, it closes the old billing account, sets up the new one, and triggers the final meter read. If you have a licensed retailer contract you also notify the retailer separately so they can transfer or cancel their commodity supply. Most move requests need at least 1 to 2 business days of notice; 5 is safer for end-of-month moves.

The move-out steps in order
1
Call Burlington Hydro

Call 905-332-1851 (or use My Account online). Give them the move date and your new address.

2
Confirm dates

1 to 2 business days minimum; allow 5 for month-end moves. Same-day service is rare.

3
Final meter read

On the move-out date, Burlington Hydro records the final reading remotely from the smart meter; no in-person visit required.

4
Final bill arrives

Burlington Hydro issues a closing bill for the period up to the move-out date. The new address bill starts under a fresh account.

Staying inside Burlington Hydro

Administrative transfer only. No physical work, no service interruption. Your RPP structure (TOU, Tiered, ULO) carries over by default; ask Burlington Hydro if you want to change it at the new address.

Moving to a different distributor

Opening a fresh account is required at the new LDC. Common destinations from Burlington include Oakville Hydro, Milton Hydro, and Alectra Utilities for Hamilton or Mississauga.

Meters, meter reading and accuracy

Burlington Hydro owns the meter at your address. Since the province-wide smart-meter rollout was completed in 2010-2011, virtually every Burlington residential and small-business address is equipped with a smart meter that supports the OEB's Time-of-Use pricing structure. The meter is the basis for both the consumption side of your bill and the choice between TOU, Tiered or Ultra-Low Overnight RPP structures.

Smart meter (AMI)
Automatic, hourly readings

Every Burlington residential address. Consumption reports back to Burlington Hydro on its own; no action from you, no estimated bills.

Suspect a fault?
Request an accuracy test

Burlington Hydro pulls the meter and tests it on a calibrated bench against Measurement Canada's tolerance.

Green Button
Your own hourly data

Download your hour-by-hour consumption via My Account or pipe it directly into an authorised third-party energy app.

How the accuracy test settles up

If the meter reads outside Measurement Canada's tolerance (typically ±2 %), the test is free and you get a billing adjustment back to the date the fault is presumed to have started. If the meter passes, the test fee is charged to you at the OEB-approved tariff rate.

Contact finder

What do you need to do with Burlington Hydro?

Pick an action. The tool shows the right phone, the right link, and what to expect. Nothing is sent anywhere.

Note: under AUC Rule 002, Alberta distributors are not required to pay automatic compensation for outages. Damage claims are evaluated case-by-case on negligence.

Compensation and damage claims: the honest version

Ontario has no automatic, statutory compensation scheme for individual customers affected by a power outage. Unlike the UK's Ofgem Guaranteed Standards, the OEB's role is to require Burlington Hydro to report its reliability performance (SAIDI, SAIFI) every year in its public scorecard. Penalties for under-performance flow from the regulator to the distributor; they do not arrive in your mailbox as a credit.

If your fridge or freezer contents spoiled, an appliance was damaged by a voltage surge, or you incurred a clear loss during an outage, you can file a damage claim with Burlington Hydro. The claim is evaluated on negligence.

Typically accepted
Distributor at fault
  • +Equipment failure (transformer, vault, network switch)
  • +Crew error during work on the network
  • +Switching incident causing voltage spike
  • +Unplanned, distributor-caused service interruption
Routinely denied
Outside distributor control
  • ×Severe weather (lightning, wind, ice storms)
  • ×Wildlife contact (squirrels, raccoons on lines)
  • ×Third-party contact (vehicle hits pole, dig-in)
  • ×Planned outages notified in advance
Faster path for most losses

Most Burlington home insurance policies cover food spoilage and surge damage at a low excess. If your loss is meaningful, the insurance route is usually faster than a denied utility claim. Keep dated receipts and photos either way. They're the only basis on which any claim can be evaluated.

Regulator and complaint escalation

If you can't resolve something directly with Burlington Hydro, there's a clear escalation ladder in Ontario. The Ontario Energy Board sits at the top as both the economic regulator and the body that handles consumer complaints; the Electrical Safety Authority covers physical-safety issues.

The escalation ladder
1
Talk to Burlington Hydro customer service

Most issues resolve here. Phone 905-332-1851 (Monday to Friday, 8:30 a.m. to 4:30 p.m.) or use the My Account portal.

2
Ask for a formal written response

If the front line can't fix it, request a written decision in writing. This creates the paper trail needed for the next step.

3
File a complaint with the OEB Consumer Protection Office

The OEB investigates complaints involving Ontario LDCs, retailers and unit sub-meter providers. The service is free.

4
OEB formal hearing or court action

Last resort. For tariff or service-quality issues you can intervene as a registered intervenor in a rate proceeding. For damage claims that are denied, civil court is the final route.

Selectra energy expert answers

Is Burlington Hydro the same company that bills me for my electricity?

Yes, for most Burlington households. Burlington Hydro is both the wires company (it owns the poles, transformers and meters across the City of Burlington) and the default supplier under Ontario's Standard Supply Service. The default per-kWh rate it charges you is the Ontario Energy Board's Regulated Price Plan (RPP), updated every six months. A different name appears on your bill only if you have signed a contract with a licensed energy retailer. Burlington Hydro also bills on behalf of Halton Region for water, on the same bi-monthly invoice.

I have a power outage. Who do I call?

Burlington Hydro has a dedicated 24/7 outage reporting line: 1-877-310-4937. You can also report and track outages through the outage portal. If you see a downed live wire or smell smoke, call 911 first, then call Burlington Hydro.

What is the Regulated Price Plan (RPP) and how does it compare with a retailer contract?

The RPP is the OEB-set default electricity rate for most residential and small-business customers in Ontario. It is updated every six months (1 May and 1 November) and you can pick one of three structures: Time-of-Use (TOU), Tiered, or Ultra-Low Overnight (ULO). A licensed retailer instead locks a fixed per-kWh rate for several years. The retailer route can hedge against future rate increases but does not change Burlington Hydro's delivery, regulatory or Global Adjustment charges on your bill.

Does Burlington Hydro pay compensation if my food spoils during an outage?

Not automatically. Ontario has no statutory automatic compensation scheme for outages. The OEB requires Burlington Hydro to report its reliability performance (SAIDI, SAIFI) in its annual scorecard, but financial consequences flow to the utility, not to you. You can file a damage claim with Burlington Hydro, but claims are evaluated case-by-case on negligence and are routinely denied when the outage was caused by weather, wildlife, third-party contact or planned work. Keep dated receipts and photos either way.

Can I choose a different electricity distributor in Burlington?

No. Your distributor is determined by your address. Every home and business inside the City of Burlington is served by Burlington Hydro. You can choose your retailer (the energy contract) but you cannot choose your wires company. Nearby Oakville is served by Oakville Hydro; Hamilton and Mississauga by Alectra Utilities; Milton by Milton Hydro.

Who do I call for a new connection or EV-charger upgrade?

Burlington Hydro. The distributor owns the physical wires and meter, so any new build, service upgrade (e.g. 100 A to 200 A for an EV charger or heat pump), temporary construction service or panel change goes through them. Call 905-332-1851 (Monday to Friday, 8:30 a.m. to 4:30 p.m.) or apply online at https://www.burlingtonhydro.com. Your electrician will also need to pull an ESA permit for the in-house wiring before Burlington Hydro can energise the new service.

Why does my electricity bill include a water charge?

Burlington Hydro provides billing services for Halton Region's water utility. That's why your bi-monthly Burlington Hydro invoice has both an electricity section and a water section. Burlington Hydro does not own or operate the water network, it simply prints the line on your bill and collects the payment on Halton Region's behalf. If you have a billing question that's specifically about water consumption or rates, the Halton Region water-services team is the right contact; for billing portal or payment issues, Burlington Hydro can help directly.