What Hydro 2000 actually does (and why your bill says "Hydro 2000" at the top)

Ontario's electricity market is structured very differently from Alberta's, and Hydro 2000 is a small-town example of how it works. Hydro 2000 wears two hats at once: it is the distributor that owns the poles, overhead lines, transformers and meters across the Township of Alfred and Plantagenet, AND it is your default supplier under Ontario's Standard Supply Service (SSS) rules. The bill that arrives at your home covers both jobs.

The per-kWh rate Hydro 2000 charges most residential and small-business customers is set by the Ontario Energy Board (OEB) twice a year in its Regulated Price Plan (RPP), with three structures to choose from: Time-of-Use, Tiered or Ultra-Low Overnight. Long-term fixed-rate retailer contracts exist, but they are a niche market in Ontario, and signing one does not change the delivery, regulatory or Global Adjustment lines on your bill, only the commodity portion. The wires that bring the electricity to your Alfred or Plantagenet address belong to Hydro 2000 regardless.

The wires + the default supply
Hydro 2000 (both roles)
  • Owns the wires, transformers and smart meters in Alfred and Plantagenet
  • Restores power after outages (small on-call crew)
  • Sends the monthly bill at the OEB's RPP rate
  • Fixed by address: every Alfred-Plantagenet property in the licensed area
Alternative: licensed retailer
Long-term fixed-rate contract
  • Replaces the commodity portion of the bill only
  • Door-to-door sales banned (ECPA 2010)
  • Delivery + Global Adjustment + regulatory unchanged
  • Hydro 2000 still owns the wires and meter
A small-town quirk worth knowing

Hydro 2000 is one of the smallest LDCs in Ontario by customer count. Its OEB-licensed service area only covers the township-owned section of Alfred and Plantagenet. Rural roads just outside the village limits often fall under Hydro One Networks, which means two neighbouring houses can have different distributors. Always check the LDC name printed at the top of your last bill before you call.

Where Hydro 2000 delivers power

In plain words: if you live or run a business inside the Township of Alfred and Plantagenet's licensed Hydro 2000 service area, Hydro 2000 is your distributor. The territory follows the township-owned legacy network, originally built to electrify the villages of Alfred and Plantagenet along Highway 17 between Ottawa and Hawkesbury. Outside that area, you are almost certainly on Hydro One.

Alfred + Plantagenet
Service area
Township-owned LDC zone
~1,300
Customer accounts
Residential + small commercial
Rural
Network type
Overhead lines + village core
OEB
Regulator
Cost-of-service framework
Covered by Hydro 2000
  • •Village of Alfred (the township seat along Highway 17)
  • •Village of Plantagenet on the South Nation River
  • •Residential, commercial and small-industrial addresses inside the township-licensed area
NOT covered (use these instead)
Communities inside Hydro 2000's territory
Alfred Plantagenet

Not sure which one applies to your address? Check your most recent electricity bill: the distributor's name and OEB licence number are printed at the top of the first page.

How Hydro 2000's charges appear on your bill

An Ontario electricity bill is broken into a handful of distinct line items, all of which appear on the same Hydro 2000 invoice. Unlike Alberta, where the commodity is billed separately by your retailer, in Ontario almost every household sees a single integrated bill where Hydro 2000 acts as both the wires company and the OEB-default supplier.

Electricity (commodity)

The per-kWh rate set by the OEB twice a year in the Regulated Price Plan. You pick one of three structures: Time-of-Use (peak/mid/off-peak), Tiered (low- and high-block) or Ultra-Low Overnight (for EV owners).

Global Adjustment

Funds the difference between the market price and the long-term contracts the IESO signed for nuclear, hydro, wind, solar and conservation. RPP customers see this rolled into the commodity rate; bigger customers see it as its own line.

Delivery

The cost of moving electricity from the IESO-controlled grid through Hydro 2000's wires to your meter. Includes a fixed monthly service charge plus a per-kWh distribution rate set by the OEB.

Regulatory charges

Small line covering OEB programs, the Wholesale Market Service Rate and a few other system-wide charges. Set by the OEB and applied uniformly across Ontario LDCs.

Ontario Electricity Rebate (OER)

A provincial credit that reduces the pre-tax subtotal by a percentage set by the government (currently around 13 %). Applied automatically to eligible residential, farm and small-business accounts.

HST

The 13 % federal-provincial sales tax applied to the post-rebate subtotal. Cannot be avoided; appears at the bottom of the bill.

Hydro 2000's delivery rate is set by the OEB under the standard Cost-of-Service / Price Cap Incentive framework used by small LDCs. Rates are filed publicly on the OEB's eFiling portal and can be examined by any customer or consumer advocate. The framework caps year-over-year increases against inflation and productivity targets.

A practical implication: if a licensed retailer offers a low fixed per-kWh rate, you'll still pay the same Hydro 2000 delivery and regulatory charges, the same Global Adjustment, the same HST. Switching retailers changes the commodity portion of your bill; switching never changes Hydro 2000's portion.

Time-of-Use (TOU)

Peak (4-7pm), mid-peak, off-peak. Best for households that can shift heavy use to evenings and weekends.

Tiered

A low block for the first ~600 kWh per month (residential), a higher block above. Best for steady, modest users.

Ultra-Low Overnight (ULO)

Very cheap from 11pm to 7am, much more expensive 4-9pm. Best for EV owners or anyone who can charge overnight.

Contact details: one small office, one number

Hydro 2000 is a three-person operation, so the contact map is simple: one main phone number handles billing, moves, account changes, new connections and outage reports. For outages reported after hours, the call is routed to an on-call technician.

Mailing & HQ address

440 rue St-Philippe
CP 370, Alfred, ON K0B 1A0

Bilingual service

English & French (Prescott-Russell)

Online

hydro2000.ca for forms and contact

For non-urgent questions you can use Hydro 2000's website at https://hydro2000.ca. Hydro 2000 publishes its annual scorecard at the OEB scorecard registry: OEB scorecard - Hydro 2000.

Report a power outage

If your power is out in Alfred or Plantagenet, call 613-679-4093 first. Hydro 2000 does not publish a live outage map, so the phone call is also how you find out whether the outage is system-wide or limited to your transformer. The website https://hydro2000.ca occasionally posts planned-outage notices for scheduled maintenance.

How it works: from your call to power back on
1
You report it

Call 613-679-4093. Have your address and account number ready.

2
On-call technician

Hydro 2000's small staff or contracted line crew is dispatched. Mutual-aid agreements with neighbouring LDCs cover bigger storm events.

3
Crew restores

Single faults are typically restored in an hour or two for a village-core address. Storm-wide outages can take longer if extra crews are needed.

4
Service back

Power is verified at the meter. Reset clocks, check freezer contents, and report any damage right away by phone.

Reliability and the OEB scorecard

Hydro 2000 reports its reliability performance to the OEB every year in its public scorecard. The headline metrics are SAIDI (average hours a customer was off per year) and SAIFI (average number of interruptions per customer per year), each measured against the OEB's distributor-specific performance standard. Because the network is small and largely overhead in a rural setting, a single storm or one substation issue can move Hydro 2000's annual numbers more than it would for a large urban LDC.

Planned outages for maintenance are normally posted at least 48 hours in advance, by mail or notice to affected addresses. If you depend on medical equipment, register with Hydro 2000 so you receive priority notification.

New connection or service upgrade

For a new build, a service upgrade (e.g. moving from 100 A to 200 A for an EV charger or heat pump), a temporary construction service, or any work that requires changes to the physical wires or meter, you deal with Hydro 2000. Call 613-679-4093 during business hours or contact them through https://hydro2000.ca. The OEB sets a 5-business-day standard for routine residential connections once all customer-side conditions are met.

What you'll need before applying
1
Site address

The civic address and the legal description of the lot inside the township.

2
Site plan

A sketch showing where you want the meter, service entrance, and run-back to the pole.

3
Service size

The amperage (100 A, 200 A, 400 A…) and voltage you need, signed off by your Master Electrician.

4
ESA permit + certification

An Electrical Safety Authority permit and ESA sign-off once the in-house wiring is done. Hydro 2000 cannot energise until ESA clears it.

Lead time
5 business days (standard)

For routine residential connections once all conditions are met. New rural service drops or service upgrades involving pole work can run longer.

Fees
OEB-approved tariff

Fixed component + per-metre charge above the contribution threshold defined in Hydro 2000's Conditions of Service.

Once the wires are in, your account opens automatically under Standard Supply Service at the OEB's Regulated Price Plan rate. You can switch your RPP structure (Time-of-Use, Tiered or Ultra-Low Overnight) at any time by contacting Hydro 2000. If you sign with a licensed retailer later, the retailer registers their contract with Hydro 2000 and the commodity rate is replaced on your next bill cycle.

Moving home, transferring or closing a service

In Alfred and Plantagenet, the move-in / move-out conversation starts with Hydro 2000 directly, not with a separate retailer. Because Hydro 2000 is the default supplier, it closes the old billing account, sets up the new one, and triggers the final meter read. If you have a licensed retailer contract you also notify the retailer separately so they can transfer or cancel their commodity supply. Most move requests need at least 1 to 2 business days of notice; 5 is safer for end-of-month moves.

The move-out steps in order
1
Call Hydro 2000

Call 613-679-4093. Give them the move date and your new address.

2
Confirm dates

1 to 2 business days minimum; allow 5 for month-end moves. Same-day service is rare.

3
Final meter read

On the move-out date, Hydro 2000 records the final reading remotely from the smart meter; no in-person visit required.

4
Final bill arrives

Hydro 2000 issues a closing bill for the period up to the move-out date. The new address bill starts under a fresh account.

Staying inside Hydro 2000

Administrative transfer only. No physical work, no service interruption. Your RPP structure (TOU, Tiered, ULO) carries over by default; ask Hydro 2000 if you want to change it at the new address.

Moving to a different distributor

Opening a fresh account is required at the new LDC. Common destinations from Alfred-Plantagenet include Hydro Ottawa, Hydro Hawkesbury, or Coopérative Hydro Embrun, with rural addresses landing on Hydro One Networks.

Meters, meter reading and accuracy

Hydro 2000 owns the meter at your address. Since the province-wide smart-meter rollout was completed in 2010-2011, virtually every Alfred-Plantagenet residential and small-business address is equipped with a smart meter that supports the OEB's Time-of-Use pricing structure. The meter is the basis for both the consumption side of your bill and the choice between TOU, Tiered or Ultra-Low Overnight RPP structures.

Smart meter (AMI)
Automatic readings

Every Alfred-Plantagenet residential address. Consumption reports back to Hydro 2000 on its own; no action from you, no estimated bills.

Suspect a fault?
Request an accuracy test

Hydro 2000 pulls the meter and tests it on a calibrated bench against Measurement Canada's tolerance.

Green Button
Your own hourly data

Where supported, you can download your hour-by-hour consumption and pipe it into an authorised third-party energy app.

How the accuracy test settles up

If the meter reads outside Measurement Canada's tolerance (typically ±2 %), the test is free and you get a billing adjustment back to the date the fault is presumed to have started. If the meter passes, the test fee is charged to you at the OEB-approved tariff rate.

Contact finder

What do you need to do with Hydro 2000?

Pick an action. The tool shows the right phone, the right link, and what to expect. Nothing is sent anywhere.

Note: under AUC Rule 002, Alberta distributors are not required to pay automatic compensation for outages. Damage claims are evaluated case-by-case on negligence.

Compensation and damage claims: the honest version

Ontario has no automatic, statutory compensation scheme for individual customers affected by a power outage. Unlike the UK's Ofgem Guaranteed Standards, the OEB's role is to require Hydro 2000 to report its reliability performance (SAIDI, SAIFI) every year in its public scorecard. Penalties for under-performance flow from the regulator to the distributor; they do not arrive in your mailbox as a credit.

If your fridge or freezer contents spoiled, an appliance was damaged by a voltage surge, or you incurred a clear loss during an outage, you can file a damage claim with Hydro 2000. The claim is evaluated on negligence.

Typically accepted
Distributor at fault
  • +Equipment failure (transformer, network switch)
  • +Crew error during work on the network
  • +Switching incident causing voltage spike
  • +Unplanned, distributor-caused service interruption
Routinely denied
Outside distributor control
  • ×Severe weather (lightning, wind, ice storms)
  • ×Wildlife contact (squirrels, raccoons on lines)
  • ×Third-party contact (vehicle hits pole, dig-in)
  • ×Planned outages notified in advance
Faster path for most losses

Most rural Ontario home insurance policies cover food spoilage and surge damage at a low excess. If your loss is meaningful, the insurance route is usually faster than a denied utility claim. Keep dated receipts and photos either way. They're the only basis on which any claim can be evaluated.

Regulator and complaint escalation

If you can't resolve something directly with Hydro 2000, there's a clear escalation ladder in Ontario. The Ontario Energy Board sits at the top as both the economic regulator and the body that handles consumer complaints; the Electrical Safety Authority covers physical-safety issues.

The escalation ladder
1
Talk to Hydro 2000 customer service

Most issues resolve here. Phone 613-679-4093 during business hours; ask for the customer service supervisor if needed.

2
Ask for a formal written response

If the front line can't fix it, request a written decision. This creates the paper trail needed for the next step.

3
File a complaint with the OEB Consumer Protection Office

The OEB investigates complaints involving Ontario LDCs, retailers and unit sub-meter providers. The service is free.

4
OEB formal hearing or court action

Last resort. For tariff or service-quality issues you can intervene as a registered intervenor. For denied damage claims, civil court is the final route.

Selectra energy expert answers

I'm in Alfred or Plantagenet and the power is out. Who do I call?

Hydro 2000 directly. Call 613-679-4093. The line is small (Hydro 2000 has just three staff for about 1,300 customers), but it is the right first point of contact for any outage on Hydro 2000's network. If you see a downed live wire or smell smoke, call 911 first. For an outage on Hydro One territory just outside the Township of Alfred and Plantagenet, call Hydro One on 1-800-434-1235 instead.

Is Hydro 2000 the company that bills me for my electricity?

Yes. In the Township of Alfred and Plantagenet, Hydro 2000 is both the wires company (it owns the poles, transformers and meters in the township) and the default supplier under Ontario's Standard Supply Service. The per-kWh rate it charges you is the Ontario Energy Board's Regulated Price Plan (RPP), updated every six months. You only see a different supplier name on your bill if you have separately signed a contract with a licensed energy retailer.

What is the Regulated Price Plan and what are my structure options?

The RPP is the OEB-set default electricity rate for residential and small-business customers in Ontario. Hydro 2000 lets you choose one of three RPP structures: Time-of-Use (TOU) (cheaper off-peak evenings and weekends), Tiered (a flat low rate up to about 600 kWh per month, then a higher block) or Ultra-Low Overnight (ULO) (very cheap from 11 p.m. to 7 a.m., much more expensive 4 p.m. to 9 p.m.). Anyone charging an EV overnight typically does best on ULO; steady, modest users on Tiered; weekend-heavy households on TOU.

Can I choose a different distributor in Alfred or Plantagenet?

No. Your distributor is determined by your address. Every home and business inside Hydro 2000's licensed service area in the Township of Alfred and Plantagenet is served by Hydro 2000, and you cannot switch wires companies. You can choose your retailer (the commodity contract) but not the LDC. Addresses on rural roads just outside the township are typically served by Hydro One Networks; if you cross the river into Hawkesbury, the LDC is Hydro Hawkesbury.

Does Hydro 2000 pay compensation if my food spoils during an outage?

Not automatically. Ontario has no statutory automatic compensation scheme for outages. The OEB requires every LDC, even a small one like Hydro 2000, to report its reliability performance (SAIDI, SAIFI) in its annual scorecard, but financial consequences flow from the regulator to the utility, not to you. You can file a damage claim with Hydro 2000, but claims are evaluated case-by-case on negligence and are routinely denied if the cause was weather, wildlife or a third-party contact. Keep dated receipts and photos either way.

Who do I call for a new connection or a 200 A service upgrade?

Hydro 2000. The distributor owns the wires and meter, so any new build, service upgrade (e.g. 100 A to 200 A for an EV charger or heat pump) or temporary construction service goes through them. Call 613-679-4093 or contact them through https://hydro2000.ca. Your licensed electrician will need to pull an ESA permit and get sign-off before Hydro 2000 can energise the new service.

Why is my Alfred-Plantagenet utility so small compared to Hydro Ottawa?

Hydro 2000 is one of the smallest LDCs in Ontario, with roughly 1,300 customers and three staff. It was incorporated in 2000 when the provincial government required Ontario municipalities to convert their hydro-electric commissions into commercial corporations under the Electricity Act. Most surrounding villages chose to amalgamate with their neighbours; the Township of Alfred and Plantagenet kept its own LDC. The OEB regulates it under the same rules as Toronto Hydro or Hydro Ottawa, just at a much smaller scale.