What Hydro Hawkesbury actually does (and why your bill says "Hydro Hawkesbury" at the top)

Ontario's electricity market is structured very differently from Alberta's, and Hydro Hawkesbury is a clear small-town example of how it works. Hydro Hawkesbury wears two hats at once: it is the distributor that owns the poles, overhead lines, transformers and meters across the Town of Hawkesbury, AND it is your default supplier under Ontario's Standard Supply Service (SSS) rules. The bill that arrives at your home covers both jobs.

The per-kWh rate Hydro Hawkesbury charges most residential and small-business customers is set by the Ontario Energy Board (OEB) twice a year in its Regulated Price Plan (RPP), with three structures to choose from: Time-of-Use, Tiered or Ultra-Low Overnight. Long-term fixed-rate retailer contracts exist, but they are a niche market in Ontario, and signing one does not change the delivery, regulatory or Global Adjustment lines on your bill, only the commodity portion. The wires that bring the electricity to your Hawkesbury address belong to Hydro Hawkesbury regardless.

The wires + the default supply
Hydro Hawkesbury (both roles)
  • Owns the wires, transformers and smart meters in Hawkesbury
  • Restores power after outages (small on-call crew + mutual aid)
  • Sends the monthly bill at the OEB's RPP rate
  • Fixed by address: every property inside the Town of Hawkesbury
Alternative: licensed retailer
Long-term fixed-rate contract
  • Replaces the commodity portion of the bill only
  • Door-to-door sales banned (ECPA 2010)
  • Delivery + Global Adjustment + regulatory unchanged
  • Hydro Hawkesbury still owns the wires and meter
A border-town quirk worth knowing

Hawkesbury sits on the Ontario side of the Ottawa River, directly facing Grenville on the Quebec side. The bridge crosses an interprovincial boundary AND a utility boundary: Hawkesbury is on Hydro Hawkesbury, Grenville is on Hydro-Québec. Streetlight problems on a Hawkesbury pole are typically handled by the Town of Hawkesbury (613-632-0106 ext. 2020), not by the LDC. The LDC handles only the actual electricity service.

Where Hydro Hawkesbury delivers power

In plain words: if you live or run a business inside the Town of Hawkesbury, Hydro Hawkesbury is your distributor. The boundary follows the town limits exactly. Just outside town (East Hawkesbury, Vankleek Hill, rural Champlain) you switch to Hydro One; across the river in Grenville, you are on Hydro-Québec.

Hawkesbury
Service area
Town of Hawkesbury limits
~5,500
Customer accounts
Residential + commercial + light industry
Town
Network type
Mixed urban + light industry
OEB
Regulator
Cost-of-service framework
Covered by Hydro Hawkesbury
  • •Town of Hawkesbury (downtown, residential neighbourhoods, light industrial parks)
  • •Hawkesbury industrial park along the Ottawa River
  • •Residential, commercial and industrial addresses inside the town limits
NOT covered (use these instead)
Communities inside Hydro Hawkesbury's territory
Hawkesbury

Not sure which one applies to your address? Check your most recent electricity bill: the distributor's name and OEB licence number are printed at the top of the first page.

How Hydro Hawkesbury's charges appear on your bill

An Ontario electricity bill is broken into a handful of distinct line items, all of which appear on the same Hydro Hawkesbury invoice. Unlike Alberta, where the commodity is billed separately by your retailer, in Ontario almost every household sees a single integrated bill where Hydro Hawkesbury acts as both the wires company and the OEB-default supplier.

Electricity (commodity)

The per-kWh rate set by the OEB twice a year in the Regulated Price Plan. You pick one of three structures: Time-of-Use (peak/mid/off-peak), Tiered (low- and high-block) or Ultra-Low Overnight (for EV owners).

Global Adjustment

Funds the difference between the market price and the long-term contracts the IESO signed for nuclear, hydro, wind, solar and conservation. RPP customers see this rolled into the commodity rate; bigger customers see it as its own line.

Delivery

The cost of moving electricity from the IESO-controlled grid through Hydro Hawkesbury's wires to your meter. Includes a fixed monthly service charge plus a per-kWh distribution rate set by the OEB.

Regulatory charges

Small line covering OEB programs, the Wholesale Market Service Rate and a few other system-wide charges. Set by the OEB and applied uniformly across Ontario LDCs.

Ontario Electricity Rebate (OER)

A provincial credit that reduces the pre-tax subtotal by a percentage set by the government (currently around 13 %). Applied automatically to eligible residential, farm and small-business accounts.

HST

The 13 % federal-provincial sales tax applied to the post-rebate subtotal. Cannot be avoided; appears at the bottom of the bill.

Hydro Hawkesbury's delivery rate is set by the OEB under the standard Cost-of-Service / Price Cap Incentive framework used by small LDCs. Rates are filed publicly on the OEB's eFiling portal and can be examined line by line by any customer or consumer advocate. The framework caps year-over-year increases against inflation and productivity targets.

A practical implication: if a licensed retailer offers a low fixed per-kWh rate, you'll still pay the same Hydro Hawkesbury delivery and regulatory charges, the same Global Adjustment, the same HST. Switching retailers changes the commodity portion of your bill; switching never changes Hydro Hawkesbury's portion.

Time-of-Use (TOU)

Peak (4-7pm), mid-peak, off-peak. Best for households that can shift heavy use to evenings and weekends.

Tiered

A low block for the first ~600 kWh per month (residential), a higher block above. Best for steady, modest users.

Ultra-Low Overnight (ULO)

Very cheap from 11pm to 7am, much more expensive 4-9pm. Best for EV owners or anyone who can charge overnight.

Contact details: one main line, one backup

Hydro Hawkesbury operates with a five-person team, so the contact map is straightforward: one main phone number for billing, moves, account changes, new connections and outage reports, plus a backup number for after-hours emergencies if the main one is busy.

Mailing & HQ address

850 Tupper Street
Hawkesbury, ON K6A 3S7

Bilingual service

English & French (Prescott-Russell)

Streetlight outages

Town of Hawkesbury 613-632-0106 ext. 2020

For non-urgent questions you can use Hydro Hawkesbury's website at https://hydrohawkesbury.ca or the dedicated outages page for planned-work notices.

Report a power outage

If your power is out in Hawkesbury, call 613-632-6689 first (backup 613-632-8603). Hydro Hawkesbury does not publish a live outage map, so the phone call is also how you find out whether the outage is system-wide or limited to your transformer. Planned-outage notices for scheduled maintenance are posted on the outages page.

How it works: from your call to power back on
1
You report it

Call 613-632-6689 (or the backup 613-632-8603). Have your address and account number ready.

2
On-call team

Hydro Hawkesbury's small staff or contracted line crew is dispatched. Mutual-aid agreements with neighbouring LDCs cover bigger storm events.

3
Crew restores

Single faults are typically restored in an hour or two in the urban core. Storm-wide outages affecting most of the town can take longer.

4
Service back

Power is verified at the meter. Reset clocks, check freezer contents, and report any damage right away by phone.

Reliability and the OEB scorecard

Hydro Hawkesbury reports its reliability performance to the OEB every year in its public scorecard. The headline metrics are SAIDI (average hours a customer was off per year) and SAIFI (average number of interruptions per customer per year), each measured against the OEB's distributor-specific performance standard. Because the town network is small and largely overhead, a single substation issue or a major storm can move Hydro Hawkesbury's annual numbers significantly compared to a larger urban LDC.

Planned outages for maintenance are normally posted at least 48 hours in advance on the outages page. If you depend on medical equipment, register with Hydro Hawkesbury so you receive priority notification.

New connection or service upgrade

For a new build, a service upgrade (e.g. moving from 100 A to 200 A for an EV charger or heat pump), a temporary construction service, or any work that requires changes to the physical wires or meter, you deal with Hydro Hawkesbury. Call 613-632-6689 during business hours or visit https://hydrohawkesbury.ca. The OEB sets a 5-business-day standard for routine residential connections once all customer-side conditions are met.

What you'll need before applying
1
Site address

The civic address and the legal description of the lot inside the Town of Hawkesbury.

2
Site plan

A sketch showing where you want the meter, service entrance, and run-back to the pole.

3
Service size

The amperage (100 A, 200 A, 400 A…) and voltage you need, signed off by your Master Electrician.

4
ESA permit + certification

An Electrical Safety Authority permit and ESA sign-off once the in-house wiring is done. Hydro Hawkesbury cannot energise until ESA clears it.

Lead time
5 business days (standard)

For routine residential connections once all conditions are met. New industrial service drops or service upgrades involving pole work can run longer.

Fees
OEB-approved tariff

Fixed component + per-metre charge above the contribution threshold defined in Hydro Hawkesbury's Conditions of Service.

Once the wires are in, your account opens automatically under Standard Supply Service at the OEB's Regulated Price Plan rate. You can switch your RPP structure (Time-of-Use, Tiered or Ultra-Low Overnight) at any time by contacting Hydro Hawkesbury. If you sign with a licensed retailer later, the retailer registers their contract with Hydro Hawkesbury and the commodity rate is replaced on your next bill cycle.

Moving home, transferring or closing a service

In Hawkesbury, the move-in / move-out conversation starts with Hydro Hawkesbury directly, not with a separate retailer. Because Hydro Hawkesbury is the default supplier, it closes the old billing account, sets up the new one, and triggers the final meter read. If you have a licensed retailer contract you also notify the retailer separately so they can transfer or cancel their commodity supply. Most move requests need at least 1 to 2 business days of notice; 5 is safer for end-of-month moves.

The move-out steps in order
1
Call Hydro Hawkesbury

Call 613-632-6689. Give them the move date and your new address.

2
Confirm dates

1 to 2 business days minimum; allow 5 for month-end moves. Same-day service is rare.

3
Final meter read

On the move-out date, Hydro Hawkesbury records the final reading remotely from the smart meter; no in-person visit required.

4
Final bill arrives

Hydro Hawkesbury issues a closing bill for the period up to the move-out date. The new address bill starts under a fresh account.

Staying inside Hydro Hawkesbury

Administrative transfer only. No physical work, no service interruption. Your RPP structure (TOU, Tiered, ULO) carries over by default; ask Hydro Hawkesbury if you want to change it at the new address.

Moving to a different distributor

Opening a fresh account is required at the new LDC. Common destinations from Hawkesbury include Hydro 2000 (Alfred-Plantagenet), Hydro Ottawa, or Hydro One Networks for rural Champlain. Moves to Grenville on the Quebec side land you on Hydro-Québec instead.

Meters, meter reading and accuracy

Hydro Hawkesbury owns the meter at your address. Since the province-wide smart-meter rollout was completed in 2010-2011, virtually every Hawkesbury residential and small-business address is equipped with a smart meter that supports the OEB's Time-of-Use pricing structure. The meter is the basis for both the consumption side of your bill and the choice between TOU, Tiered or Ultra-Low Overnight RPP structures.

Smart meter (AMI)
Automatic readings

Every Hawkesbury residential address. Consumption reports back to Hydro Hawkesbury on its own; no action from you, no estimated bills.

Suspect a fault?
Request an accuracy test

Hydro Hawkesbury pulls the meter and tests it on a calibrated bench against Measurement Canada's tolerance.

Green Button
Your own hourly data

Where supported, you can download your hour-by-hour consumption and pipe it into an authorised third-party energy app.

How the accuracy test settles up

If the meter reads outside Measurement Canada's tolerance (typically ±2 %), the test is free and you get a billing adjustment back to the date the fault is presumed to have started. If the meter passes, the test fee is charged to you at the OEB-approved tariff rate.

Contact finder

What do you need to do with Hydro Hawkesbury?

Pick an action. The tool shows the right phone, the right link, and what to expect. Nothing is sent anywhere.

Note: under AUC Rule 002, Alberta distributors are not required to pay automatic compensation for outages. Damage claims are evaluated case-by-case on negligence.

Compensation and damage claims: the honest version

Ontario has no automatic, statutory compensation scheme for individual customers affected by a power outage. Unlike the UK's Ofgem Guaranteed Standards, the OEB's role is to require Hydro Hawkesbury to report its reliability performance (SAIDI, SAIFI) every year in its public scorecard. Penalties for under-performance flow from the regulator to the distributor; they do not arrive in your mailbox as a credit.

If your fridge or freezer contents spoiled, an appliance was damaged by a voltage surge, or you incurred a clear loss during an outage, you can file a damage claim with Hydro Hawkesbury. The claim is evaluated on negligence.

Typically accepted
Distributor at fault
  • +Equipment failure (transformer, network switch)
  • +Crew error during work on the network
  • +Switching incident causing voltage spike
  • +Unplanned, distributor-caused service interruption
Routinely denied
Outside distributor control
  • ×Severe weather (lightning, wind, ice storms)
  • ×Wildlife contact (squirrels, raccoons on lines)
  • ×Third-party contact (vehicle hits pole, dig-in)
  • ×Planned outages notified in advance
Faster path for most losses

Most Ontario home insurance policies cover food spoilage and surge damage at a low excess. If your loss is meaningful, the insurance route is usually faster than a denied utility claim. Keep dated receipts and photos either way. They're the only basis on which any claim can be evaluated.

Regulator and complaint escalation

If you can't resolve something directly with Hydro Hawkesbury, there's a clear escalation ladder in Ontario. The Ontario Energy Board sits at the top as both the economic regulator and the body that handles consumer complaints; the Electrical Safety Authority covers physical-safety issues.

The escalation ladder
1
Talk to Hydro Hawkesbury customer service

Most issues resolve here. Phone 613-632-6689 during business hours; ask for the customer service supervisor if needed.

2
Ask for a formal written response

If the front line can't fix it, request a written decision. This creates the paper trail needed for the next step.

3
File a complaint with the OEB Consumer Protection Office

The OEB investigates complaints involving Ontario LDCs, retailers and unit sub-meter providers. The service is free.

4
OEB formal hearing or court action

Last resort. For tariff or service-quality issues you can intervene as a registered intervenor. For denied damage claims, civil court is the final route.

Selectra energy expert answers

I'm in Hawkesbury and the power is out. Who do I call?

Hydro Hawkesbury directly. Call 613-632-6689 (backup line 613-632-8603 if the main one is busy). The phone line is the primary channel because Hydro Hawkesbury does not publish a live outage map. If you see a downed live wire or smell smoke, call 911 first. For a streetlight outage on a municipal pole, contact the Town of Hawkesbury directly at 613-632-0106 ext. 2020.

Is Hydro Hawkesbury the company that bills me for my electricity?

Yes. In the Town of Hawkesbury, Hydro Hawkesbury is both the wires company (it owns the poles, transformers and meters in the town) and the default supplier under Ontario's Standard Supply Service. The per-kWh rate it charges you is the Ontario Energy Board's Regulated Price Plan (RPP), updated every six months. You only see a different supplier name on your bill if you have separately signed a contract with a licensed energy retailer.

What is the Regulated Price Plan and which structure should I pick?

The RPP is the OEB-set default electricity rate for residential and small-business customers in Ontario. Hydro Hawkesbury offers three RPP structures: Time-of-Use (TOU) (cheaper off-peak), Tiered (low block up to about 600 kWh per month, higher block above) or Ultra-Low Overnight (ULO) (very cheap 11 p.m. to 7 a.m., expensive 4 p.m. to 9 p.m.). EV owners typically save the most on ULO; steady, modest users on Tiered; weekend-heavy households on TOU.

Can I choose a different distributor in Hawkesbury?

No. Your distributor is determined by your address. Every home and business inside the Town of Hawkesbury is served by Hydro Hawkesbury, and you cannot switch wires companies. You can choose your retailer (the commodity contract) but not the LDC. If you cross out of town to Vankleek Hill or rural roads outside the town limits, the LDC is usually Hydro One; if you cross the river to Grenville, you are in Quebec on Hydro-Québec.

Does Hydro Hawkesbury pay compensation if my food spoils during an outage?

Not automatically. Ontario has no statutory automatic compensation scheme for outages. The OEB requires Hydro Hawkesbury to report its reliability performance (SAIDI, SAIFI) in its annual scorecard, but financial consequences flow from the regulator to the utility, not to you. You can file a damage claim, but claims are evaluated on negligence and are routinely denied if the cause was weather, wildlife or a third-party contact. Keep dated receipts and photos either way.

Who do I call for a new connection or a 200 A service upgrade?

Hydro Hawkesbury. The distributor owns the wires and meter, so any new build, service upgrade (e.g. 100 A to 200 A for an EV charger or heat pump) or temporary construction service goes through them. Call 613-632-6689 during business hours or visit https://hydrohawkesbury.ca. Your licensed electrician will need to pull an ESA permit and get sign-off before Hydro Hawkesbury can energise the new service.

Why is Hydro Hawkesbury still its own utility instead of merging with a neighbour?

When Ontario forced municipal hydro commissions to convert into commercial corporations in 2000, the Town of Hawkesbury chose to keep its utility wholly municipal rather than merge with neighbours. The roots go back further: the Hawkesbury Hydro-Electric Commission was created on 18 October 1954. The town remains the sole shareholder, and the OEB regulates it under the same framework as every other Ontario LDC, just at a much smaller scale.