What Hydro One Networks actually does for Cat Lake (and why your bill says Hydro One)

Ontario's electricity market normally splits cleanly between mainland distributors connected to the IESO-controlled grid and a small handful of isolated communities that produce their own power on site. Cat Lake First Nation, on the shores of Cat Lake about 180 km north of Sioux Lookout, is one of those isolated communities. The wires, transformers and meters in the community belong to Hydro One Networks Inc. under an OEB-issued interim distribution licence (ED-2006-0181) that was first granted in 2006 and has been renewed every few years since.

The generation side, by contrast, is owned by Cat Lake Power Generation Inc. and runs on diesel engines. Hydro One Networks does not own the generators but it is the company that bills you for the electricity, restores power after an outage and manages new connections. Because Cat Lake is administered through the mainland Hydro One Networks licence (not through the separate Hydro One Remote Communities Inc. subsidiary, which covers 21 other isolated communities), the OEB rate schedule and customer-service phone tree are the same as for any other Hydro One Networks customer in Ontario.

Hydro One Networks (the wires + bill)
Distributor and default supplier
  • Owns the in-community wires, transformers and meters
  • Operates the 24/7 outage line and dispatches crews
  • Sends the monthly bill at the OEB rate
  • Interim distribution licence ED-2006-0181, renewed since 2006
Cat Lake Power Generation Inc.
Local diesel generation
  • Owns and operates the diesel generators on site
  • Not connected to the IESO-controlled provincial grid
  • True cost subsidised through the OEB's RRRP charge
  • Generation does not appear separately on your bill
Cat Lake is NOT served by Hydro One Remote Communities Inc.

It is a common confusion. Hydro One has a separate subsidiary, Hydro One Remote Communities Inc., that covers 21 other isolated communities in the Far North. Cat Lake was assigned to Hydro One Networks in 2006 because of how its distribution assets were transferred at the time. Practically it makes little difference for residents (same phone numbers, same OEB framework), but the rate schedule on file at the OEB is the Hydro One Networks one.

Where Hydro One Networks delivers power for Cat Lake

In plain words: the licensed service area is the Cat Lake First Nation reserve, an isolated fly-in community on the shores of Cat Lake in northwestern Ontario. There are no road connections to the south for most of the year and no transmission lines to the IESO grid. Every customer inside the community boundary is served by Hydro One Networks under the interim distribution licence; there is no overlap with any other LDC.

Cat Lake
Service area
First Nation reserve, NW Ontario
~150
Customer accounts
~650 registered band members
Off-grid
Network type
Diesel generation, no IESO link
OEB
Regulator
Interim licence ED-2006-0181
Covered by Hydro One Networks (Cat Lake)
  • •Cat Lake First Nation reserve and its residential, school and band-office services
  • •Local stores, nursing station and community infrastructure inside the reserve
  • •Connection at the diesel generating station owned by Cat Lake Power Generation Inc.
NOT covered by this licence
  • •Other isolated First Nations such as Pikangikum, Sandy Lake, Bearskin Lake → Hydro One Remote Communities
  • •Sioux Lookout, Dryden and Red Lake → Hydro One Networks mainland licence
  • •Thunder Bay → Synergy North
Community inside the licensed territory
Cat Lake First Nation

Not sure which one applies to your address? Check your most recent electricity bill: the distributor's name and OEB licence number are printed at the top of the first page.

How Hydro One's charges appear on your Cat Lake bill

An Ontario electricity bill is broken into a handful of distinct line items, all of which appear on the same Hydro One Networks invoice for Cat Lake. The bill looks the same as any other Hydro One customer's, even though the underlying generation in the community is diesel rather than grid power.

Electricity (commodity)

The per-kWh rate set by the OEB twice a year. Cat Lake customers are billed at the Hydro One Networks residential rate; the actual cost of diesel generation is partially subsidised by the OEB's Rural or Remote Rate Protection (RRRP) charge that every Ontario bill pays into.

Rural or Remote Rate Protection

The province-wide cross-subsidy that flattens the cost gap between dense urban distribution (e.g. Toronto Hydro) and isolated diesel grids like Cat Lake. Not a line on YOUR bill: it shows up on every other Ontario customer's bill instead.

Delivery

The cost of moving electricity from the local diesel plant through Hydro One's wires to your meter. Includes a fixed monthly service charge plus a per-kWh distribution rate set by the OEB.

Regulatory charges

Small line covering OEB programs and a few other system-wide charges. Set by the OEB and applied uniformly across Ontario LDCs.

Ontario Electricity Rebate (OER)

A provincial credit that reduces the pre-tax subtotal by a percentage set by the government (currently around 13 %). Applied automatically to eligible residential, farm and small-business accounts.

HST

The 13 % federal-provincial sales tax applied to the post-rebate subtotal. Appears at the bottom of the bill.

Hydro One Networks files its rates with the OEB under the incentive rate-setting framework (most recently EB-2023-0030 for 2024 rates and beyond). Rates are public and can be examined line by line by any customer or intervenor. Because Cat Lake is administered under this same Hydro One Networks licence, the rate schedule is identical to what other Hydro One Networks customers see in the rest of the province; the OEB then uses RRRP to socialise the diesel cost premium across all Ontario ratepayers.

A practical implication: signing with a licensed retailer would change only the commodity portion of your bill. The delivery, regulatory and HST lines (which are most of the bill in an isolated community) would stay the same. In practice retail offers are extremely rare in Far North communities.

Time-of-Use (TOU)

Peak (4-7pm), mid-peak, off-peak. Available to Hydro One residential customers; uptake in isolated communities is limited.

Tiered

A low block for the first kWh per month, a higher block above. The most common default choice in remote and rural areas.

Ultra-Low Overnight (ULO)

Very cheap 11pm-7am, much more expensive 4-9pm. Optional, mostly useful for households that have heavy overnight loads.

Contact details: Hydro One's province-wide phone tree

Cat Lake customers reach Hydro One Networks through its province-wide customer system. The 24/7 emergency line handles outages, downed wires and any safety emergencies; the customer service line handles billing, moves, account changes and new connections.

Hydro One Networks HQ

483 Bay Street, South Tower
7th Floor, Toronto, ON M5G 2P5

My Account portal

Bills, usage, payments and outage history online at hydroone.com

Mobile app

iOS & Android, with outage map and push notifications

For non-urgent questions you can also use Hydro One's online tools: the live outage map, the outage hub or the My Account portal at https://www.hydroone.com. The local band office in Cat Lake can also help relay outage information when phone or internet service is intermittent.

Report a power outage in Cat Lake

If your power is out, call 1-800-434-1235, Hydro One's 24/7 line. You can also report and track outages on the Hydro One outage map. Because Cat Lake is an isolated community, restoration depends on whether the problem is in the local distribution wires (fixed in minutes to hours by the on-site crew) or at the diesel generating station (which may take longer if a generator needs to be returned to service).

How it works: from your call to power back on
1
You report it

Call 1-800-434-1235 or use the Hydro One outage map. Have your address and account number ready.

2
Dispatch confirms

Hydro One coordinates with the on-site crew in Cat Lake and Cat Lake Power Generation Inc. to locate the fault and decide who responds.

3
Crew restores

Distribution faults (broken pole, blown transformer): minutes to hours. Generation faults at the diesel plant: longer, as backup units may need to be started.

4
Service back

Power is verified at the smart meter. Reset clocks, check freezer contents, and report any damage right away via Hydro One's claims form.

Reliability context for Cat Lake

Hydro One Networks reports reliability to the OEB on a province-wide basis; Cat Lake performance is rolled into the Hydro One Networks scorecard rather than reported separately. In any isolated community, the dominant reliability risks are weather (winter storms, ice loading on poles), wildlife and the availability of the local diesel generators. Planned outages for diesel maintenance or fuel delivery are normally posted at least 48 hours in advance via the band office and on the Hydro One outage hub.

If you depend on medical equipment, register with Hydro One's medical-needs program so you receive priority notification of planned work.

New connection or service upgrade in Cat Lake

For a new build, a service upgrade or any work that requires changes to the physical wires or meter inside Cat Lake, you deal with Hydro One Networks. Start at https://www.hydroone.com or call 1-888-664-9376. In a fly-in community, lead times depend heavily on materials shipping (winter road, barge or air freight) and on coordination with Cat Lake Power Generation Inc. for any additional load on the diesel plant.

What you'll need before applying
1
Site address

The lot description and any band council approvals required for the build inside the reserve.

2
Site plan

A sketch showing where you want the meter, service entrance, and run-back to the nearest pole or pad.

3
Service size

The amperage (100 A, 200 A…) and voltage you need, signed off by your Master Electrician.

4
ESA permit + certification

An Electrical Safety Authority permit and ESA sign-off once the in-house wiring is done. Hydro One cannot energise until ESA clears it.

Lead time
Weeks to months (community-dependent)

Most isolated communities depend on a winter road or barge shipping window; complex projects line up with that calendar.

Fees
OEB-approved tariff

Fixed component + per-metre charge above the contribution threshold defined in Hydro One's Conditions of Service.

Once the wires are in, your account opens automatically at Hydro One Networks' Standard Supply Service rate. You can change between Time-of-Use, Tiered and ULO at any time by calling Hydro One's customer service line.

Moving home, transferring or closing a service

In Cat Lake, the move-in / move-out conversation starts with Hydro One Networks directly. Because Hydro One is the default supplier, it closes the old billing account, sets up the new one and triggers the final meter read. Most move requests need at least 1 to 2 business days of notice; allow more around the winter holiday window.

The move-out steps in order
1
Call Hydro One

Call 1-888-664-9376 or use My Account online. Give them the move date and your new address.

2
Confirm dates

1 to 2 business days minimum; allow more around the holiday season. Same-day service is rare.

3
Final meter read

Hydro One records the final reading on the move-out date. In isolated communities this may require an on-site visit if the meter is not yet on the smart-meter network.

4
Final bill arrives

Hydro One issues a closing bill for the period up to the move-out date. The new address bill starts under a fresh account.

Staying inside Cat Lake (same LDC)

Administrative transfer only. No physical work, no service interruption. Your RPP structure carries over by default; ask Hydro One if you want to change it at the new address.

Moving to a different distributor

Opening a fresh account is required at the new LDC. Common destinations from Cat Lake include other isolated communities served by Hydro One Remote Communities or mainland Hydro One Networks territory in northwestern Ontario.

Meters, meter reading and accuracy

Hydro One Networks owns the meter at your address. In Cat Lake and other isolated communities, the smart-meter rollout has lagged behind the rest of the province: many homes still have legacy electromechanical meters that require an on-site read, although Hydro One has been progressively upgrading them. The meter is the basis for both the consumption side of your bill and the choice between TOU, Tiered or Ultra-Low Overnight RPP structures.

Smart meter (AMI)
Where deployed

Newer homes and recent upgrades use smart meters with automatic hourly reads. No estimated bills where they are installed.

Legacy meter
Still common in Cat Lake

Older accounts may have legacy meters with on-site reads. Bills can include estimated charges between reads.

Suspect a fault?
Request an accuracy test

Hydro One pulls the meter and tests it on a calibrated bench against Measurement Canada's tolerance.

How the accuracy test settles up

If the meter reads outside Measurement Canada's tolerance (typically ±2 %), the test is free and you get a billing adjustment back to the date the fault is presumed to have started. If the meter passes, the test fee is charged to you at the OEB-approved tariff rate.

Contact finder

What do you need to do with Hydro One Networks (Cat Lake)?

Pick an action. The tool shows the right phone, the right link, and what to expect. Nothing is sent anywhere.

Note: under AUC Rule 002, Alberta distributors are not required to pay automatic compensation for outages. Damage claims are evaluated case-by-case on negligence.

Compensation and damage claims: the honest version

Ontario has no automatic, statutory compensation scheme for individual customers affected by a power outage. Unlike the UK's Ofgem Guaranteed Standards, the OEB's role is to require Hydro One to report its reliability performance every year in its public scorecard. Penalties for under-performance flow from the regulator to the distributor; they do not arrive in your mailbox as a credit.

If your fridge or freezer contents spoiled, an appliance was damaged by a voltage surge, or you incurred a clear loss during an outage, you can file a damage claim with Hydro One. The claim is evaluated on negligence.

Typically accepted
Distributor at fault
  • +Equipment failure (transformer, pole, network switch)
  • +Crew error during work on the local network
  • +Switching incident causing voltage spike
  • +Unplanned, distributor-caused service interruption
Routinely denied
Outside distributor control
  • ×Severe weather (lightning, wind, ice storms)
  • ×Wildlife contact on lines
  • ×Diesel generator outages handled by Cat Lake Power Generation Inc.
  • ×Planned outages notified in advance
Faster path for most losses

Most home insurance policies cover food spoilage and surge damage at a low excess. If your loss is meaningful, the insurance route is usually faster than a denied utility claim. Keep dated receipts and photos either way; they are the only basis on which any claim can be evaluated.

Regulator and complaint escalation

If you can't resolve something directly with Hydro One, there's a clear escalation ladder in Ontario. The Ontario Energy Board sits at the top as both the economic regulator and the body that handles consumer complaints; the Electrical Safety Authority covers physical-safety issues.

The escalation ladder
1
Talk to Hydro One customer service

Most issues resolve here. Phone 1-888-664-9376 (Monday to Friday, 7:30 a.m. to 8:00 p.m.) or use the My Account portal.

2
Ask for a formal written response

If the front line can't fix it, request a written decision in writing. This creates the paper trail needed for the next step.

3
File a complaint with the OEB Consumer Protection Office

The OEB investigates complaints involving Ontario LDCs, retailers and unit sub-meter providers. The service is free.

4
OEB formal hearing or court action

Last resort. For tariff or licence-renewal issues you can intervene as a registered intervenor. For damage claims that are denied, civil court is the final route.

Selectra energy expert answers

Why does my Cat Lake bill say Hydro One on the top?

Because Hydro One Networks Inc. holds the OEB-issued distribution licence for the Cat Lake community (originally interim licence ED-2006-0181, renewed since 2006). In 2006 the Ontario Energy Board transferred the Cat Lake Public Utility distribution assets to Hydro One Networks, while the generation side stayed with Cat Lake Power Generation Inc. Hydro One owns the wires and meters and bills you for the electricity that flows through them.

Power is out in Cat Lake. Who do I call?

Hydro One's 24/7 emergency line, 1-800-434-1235. The same number handles every Hydro One Networks customer in Ontario, including the Cat Lake community. You can also report and track outages on the Hydro One outage map. For a downed live wire, call 911 first.

Is Cat Lake on the provincial grid or off-grid?

Cat Lake is an isolated, off-grid community on the shores of Cat Lake, about 180 km north of Sioux Lookout. There is no transmission line to the IESO-controlled grid; electricity is generated locally by diesel engines owned by Cat Lake Power Generation Inc. and delivered through wires owned and operated by Hydro One Networks.

Is my rate the same as Hydro One's mainland residential customers?

Cat Lake follows the rate schedules that the OEB approves for Hydro One Networks. Because the community is isolated, the true cost of diesel generation is much higher than the rate the household sees: the gap is bridged by the OEB's Rural or Remote Rate Protection (RRRP) charge, which every Ontario electricity bill helps fund. So in practice Cat Lake customers pay a residential rate broadly comparable to other Hydro One customers, with the diesel premium socialised province-wide.

Does Hydro One pay compensation if my food spoils during an outage?

Not automatically. Ontario has no statutory automatic compensation scheme for outages, unlike the UK's Ofgem Guaranteed Standards. The OEB requires Hydro One to report reliability performance every year. You can file a damage claim, but it is evaluated case-by-case on negligence and is routinely denied when the cause is weather, wildlife, third-party contact or planned work. Keep receipts and timestamps.

Can I choose another distributor in Cat Lake?

No. Your distributor is fixed by address. Hydro One Networks holds the interim distribution licence for Cat Lake and there is no overlapping LDC. You can in principle sign with a licensed energy retailer for the commodity portion of your bill, but the wires, the meter and the delivery line items will always be Hydro One's.

Who do I call for a new connection or service upgrade?

Hydro One Networks. Call 1-888-664-9376 (Monday to Friday, 7:30 a.m. to 8:00 p.m.) or apply online at https://www.hydroone.com. Your electrician will also need to pull an ESA permit for the in-house wiring before Hydro One can energise the service.