What Hydro-Sherbrooke actually does (and why Sherbrooke isn't on Hydro-Quebec)

If you've moved to Sherbrooke from anywhere else in Quebec, the first thing to know is that you're not a Hydro-Quebec customer: the City of Sherbrooke runs its own electricity service. Hydro-Sherbrooke is a department of the municipality, with about 84,000 customer accounts across the six boroughs (Brompton, Fleurimont, Jacques-Cartier, Lennoxville, Mont-Bellevue and Rock Forest-Saint-Elie-Deauville). It buys bulk power wholesale from Hydro-Quebec, runs its own substations and distribution wires, and bills you on a Sherbrooke statement, not a Hydro-Quebec one. There is no separate retailer to choose.

The historical reason is that Sherbrooke founded a municipal electricity service in 1908, more than three decades before Hydro-Quebec existed. When the Quebec government created Hydro-Quebec in 1944 and nationalised most private utilities in 1963, the municipal services that were already up and running were allowed to continue. Hydro-Sherbrooke is the largest of those survivors. Its rates are approved by the Regie de l'energie du Quebec and tend to track Hydro-Quebec Rate D very closely, since the bulk supply Sherbrooke buys from Hydro-Quebec at the wholesale L tariff is the main cost driver.

Hydro-Sherbrooke does everything inside city limits
Wires + meter + bill
  • Buys bulk power from Hydro-Quebec at the wholesale L tariff
  • Owns the wires, poles, transformers, substations and meters inside Sherbrooke
  • Operates several small hydroelectric stations on the Saint-Francois and Magog rivers
  • Bills you on a City of Sherbrooke statement, not a Hydro-Quebec one
You don't choose a retailer
No competitive market in QC
  • ×Inside Sherbrooke city limits, your provider is Hydro-Sherbrooke, full stop
  • ×No commodity contracts, no fixed vs variable plans
  • ×Rates are filed with the Regie de l'energie and approved publicly
  • ×To leave the municipal utility you have to physically move out of Sherbrooke

Where Hydro-Sherbrooke delivers power

In plain words: if your address is inside the City of Sherbrooke as it has existed since the 2002 municipal amalgamation, Hydro-Sherbrooke is your provider. That covers all six boroughs across about 366 km²: Brompton, Fleurimont, Jacques-Cartier, Lennoxville, Mont-Bellevue and Rock Forest-Saint-Elie-Deauville. Step outside the city boundary (for example into Stoke, Saint-Denis-de-Brompton or East Angus) and you become a Hydro-Quebec customer.

~366 km²
Land area served
City of Sherbrooke
~172,000
People served
Across all 6 boroughs
~84,000
Customer accounts
Homes, business, industrial
6
Boroughs served
All of post-2002 Sherbrooke
Covered by Hydro-Sherbrooke
  • •Borough of Jacques-Cartier: downtown Sherbrooke and the historic core north of the Magog River
  • •Borough of Mont-Bellevue: south of the Magog River, around Universite de Sherbrooke and Bishop's
  • •Borough of Fleurimont: east end including Centre hospitalier universitaire de Sherbrooke (CHUS)
  • •Boroughs of Brompton, Lennoxville and Rock Forest-Saint-Elie-Deauville: the former towns that merged into Sherbrooke in 2002
NOT covered (use these instead)
  • •Outside the city boundary (Stoke, Saint-Denis-de-Brompton, Compton, East Angus, Magog rural) → Hydro-Quebec
  • •City of Magog (next municipality south-west, around Lake Memphremagog) → Hydro-Magog
  • •City of Coaticook (south of Sherbrooke, near the Vermont border) → Hydro-Coaticook
  • •Rest of Estrie outside city limits → Hydro-Quebec
Localities and sectors inside Hydro-Sherbrooke's territory
Sherbrooke Lennoxville Bromptonville Rock Forest Deauville

Not in Hydro-Sherbrooke's territory? Pick your distributor

Not sure which one? Check the top of your most recent electricity bill: if it says "Ville de Sherbrooke - Hydro-Sherbrooke", you're in the municipal utility's territory.

How Hydro-Sherbrooke's residential rates work

Because Hydro-Sherbrooke is integrated (it buys bulk power, runs the wires and bills the customer), your monthly bill is much simpler than in Alberta. There is no separate "delivery" half to compare against the commodity. Instead, Regie-approved rates combine everything into a single per-kWh price that depends on how much you use, plus a small fixed daily charge. The schedule everyone defaults to is the Hydro-Sherbrooke residential rate, which tracks the Hydro-Quebec Rate D structure very closely.

System access charge

A fixed amount per day (around 41 ¢), regardless of consumption. Covers metering, billing and customer support. Mirrors the Hydro-Quebec Rate D fixed charge almost exactly.

Step 1 energy charge

Applies to the first 40 kWh used per day. A low per-kWh rate (about 7.8 ¢/kWh as of 2026). Designed to cover baseline residential consumption.

Step 2 energy charge

A higher per-kWh rate (about 10 ¢/kWh as of 2026) on every kWh above the 40 kWh/day threshold. Encourages conservation, especially in winter when electric heating drives consumption up.

Bulk supply cost

Sherbrooke buys its energy from Hydro-Quebec at the wholesale L tariff. Movements in the L tariff drive the headline rate change Hydro-Sherbrooke proposes to the Regie each year.

Municipal investment

Profits from the utility flow back into the City of Sherbrooke general fund, which historically helped finance roads, water and recreation infrastructure. The pricing impact is small but real.

GST & QST

Federal GST (5 %) and Quebec Sales Tax (9.975 %) apply to the electricity portion of the bill. Together they add roughly 15 % on top of the energy and access charges at the bottom of the statement.

The Regie de l'energie reviews Hydro-Sherbrooke's rates each time the municipal utility files a revenue requirement application. In practice the municipal residential rates track Hydro-Quebec Rate D very closely, because the bulk supply cost dominates. The current schedules are published on the Hydro-Sherbrooke section of sherbrooke.ca.

Contact details: emergency line first

Hydro-Sherbrooke uses a single phone number for both emergency and general service. The IVR routes 24/7 outage reports to the on-call dispatcher and routes account and billing questions to the day-shift counter agents. You can also use the city outage status page for live updates or visit sherbrooke.ca/Hydro-Sherbrooke for service requests.

Report a power outage

If your power is out, the fastest path is to call 819-821-5400 or check the city outage map. The dispatcher logs the address, cross-references it with field telemetry, and assigns a crew if the cause isn't already identified. Do not call Hydro-Quebec by mistake: the operator will redirect you, but it costs you minutes.

How it works: from your call to power back on
1
You report it

Call 819-821-5400 or use the city outage form. Have your address and account number ready.

2
Dispatch confirms

The Sherbrooke control room pinpoints which substation or feeder is affected and assigns a crew or pole patrol.

3
Crew restores

Urban faults inside Sherbrooke typically resolve in minutes to a few hours, since the network is compact. Storm-wide events take longer and may involve crews from Hydro-Quebec.

4
Service back

Power is verified at the meter. Reset clocks, check freezer, and report any damage right away to the Hydro-Sherbrooke counter under the Conditions de service.

Hydro-Sherbrooke reports its reliability performance to the Regie de l'energie each year. The two headline metrics are SAIDI (average minutes a customer was off per year) and SAIFI (average number of outages per customer per year). Sherbrooke benefits from a relatively compact urban network and a high proportion of underground feeders downtown, so urban SAIDI tends to be lower than the Quebec average, though freezing rain and winter ice storms in Estrie can still drive seasonal spikes.

Planned outages for maintenance are normally posted 48 to 72 hours in advance on the city website and notified to affected addresses. If you depend on medical equipment, register that with Hydro-Sherbrooke so you receive priority notification before planned work.

New connection or service upgrade

For a new build, a service upgrade (e.g. moving from 100 A to 200 A to support an EV charger and a heat pump), a temporary construction service, or any work that requires changes to the physical wires or meter inside Sherbrooke city limits, you deal with Hydro-Sherbrooke. Start at sherbrooke.ca or call 819-821-5400.

What you'll need before applying
1
Site address

The civic address and the legal land description (lot number, cadastre) for the parcel.

2
Site plan

A sketch showing where you want the meter, the service entrance and the run-back to the pole or pad-mounted transformer.

3
Service size

The amperage (100 A, 200 A, 400 A…) and voltage you need, with a load calculation signed off by your master electrician.

4
Permits + certification

City of Sherbrooke building permit and a Regie du batiment du Quebec (RBQ) electrical permit pulled by a licensed master electrician, with the wiring sign-off once the in-house work is done.

Lead time
3 to 10 weeks

Standard urban residential inside Sherbrooke. Larger industrial or new-subdivision projects with new transformers can take 3 to 6 months.

Fees
Regie-approved tariff

Service charge plus per-metre extension above the contribution threshold defined in the city Conditions de service.

Once the wires are in and Hydro-Sherbrooke has energised the service, your billing account opens automatically under the municipal residential rate. There's no separate retailer to sign up with: Hydro-Sherbrooke handles the connection, the meter and the bill on a City of Sherbrooke statement.

Moving home, transferring or closing a service

Inside Sherbrooke city limits, the move-in / move-out conversation is a single call (or a single online form) to Hydro-Sherbrooke. There's no second retailer to coordinate with. Most moves can be set up online through sherbrooke.ca with at least 2 business days' notice. Five days is safer for end-of-month moves and especially around 1 July, traditionally Quebec's national moving day.

The move-out steps in order
1
Notify Hydro-Sherbrooke

Online through sherbrooke.ca or by phone. Give them the move date, the old address and the new one.

2
Confirm dates

2 business days minimum; allow 5 for month-end moves and especially around 1 July. Same-day disconnections are rare.

3
Final meter read

On the move-out date, Hydro-Sherbrooke records the final reading from the smart meter.

4
Final bill arrives

Hydro-Sherbrooke issues a closing bill for the period up to the move-out date. If you stay in Sherbrooke, the new address bill starts under the same customer file.

Staying inside Sherbrooke

Administrative transfer only. No physical work, no service interruption. The city online portal can handle the whole move; you keep the same customer file.

Moving outside Sherbrooke

Opening a fresh account is required. If you're moving outside the city boundary into a Hydro-Quebec area, sign up directly with Hydro-Quebec — Hydro-Sherbrooke can't roll the contract across.

Meters, meter reading and accuracy

Hydro-Sherbrooke has rolled out smart meters across the city. Almost every residential address now has an AMI (Advanced Metering Infrastructure) meter that reports consumption back to the utility automatically, with no need for in-person reads and no estimated bills.

Smart meter (AMI)
Automatic readings

Most residential addresses. Consumption reports back to Hydro-Sherbrooke on its own; you can see daily use in your online file.

Suspect a fault?
Request an accuracy test

Hydro-Sherbrooke pulls the meter and tests it on a calibrated bench against Measurement Canada's tolerance.

Non-communicating meter
Manual reading option

A small minority of customers chose a non-communicating meter. A monthly fee applies and a meter reader visits to take the reading manually.

How the accuracy test settles up

If the meter reads outside Measurement Canada's tolerance (typically ±2 %), the test is free and you get a billing adjustment. If it passes, the test fee is charged to you at the Regie-approved tariff rate.

Contact finder

What do you need to do with Hydro-Sherbrooke?

Pick an action. The tool shows the right phone, the right link, and what to expect. Nothing is sent anywhere.

Note: under AUC Rule 002, Alberta distributors are not required to pay automatic compensation for outages. Damage claims are evaluated case-by-case on negligence.

Compensation and damage claims: the honest version

This is the section where European-style explainers tend to mislead. Quebec has no automatic, statutory compensation scheme for individual customers affected by a power outage. Unlike the UK's Ofgem Guaranteed Standards (which pay an automatic amount after defined outage durations), Regie de l'energie oversight of Hydro-Sherbrooke focuses on reliability reporting (SAIDI, SAIFI) and on rate-design fairness. The penalty for under-performance flows from the regulator into the next rate case, not from the distributor to you.

If your fridge or freezer contents spoiled, an appliance was damaged by a voltage surge, or you incurred a clear loss during an outage, you can file a damage claim with Hydro-Sherbrooke under the city Conditions de service. The claim is evaluated on negligence, and weather events are typically excluded under the force majeure clause.

Typically accepted
Distributor at fault
  • +Equipment failure (transformer, switch, cable)
  • +Crew error during work on the network
  • +Switching incident causing voltage spike
  • +Unplanned, distributor-caused service interruption
Routinely denied
Outside distributor control
  • ×Severe weather (wind, freezing rain, ice storms)
  • ×Wildlife contact (squirrels, birds, raccoons on lines)
  • ×Third-party contact (vehicle hits pole, dig-in)
  • ×Planned outages notified in advance
Faster path for most losses

Most Quebec home insurance policies cover food spoilage and surge damage at a low deductible. If your loss is meaningful, the insurance route is usually faster than a denied utility claim. Keep dated receipts and photos either way. They're the only basis on which a claim can be evaluated.

Regulator and complaint escalation

If you can't resolve something directly with Hydro-Sherbrooke, there's a clear escalation ladder in Quebec. The lead regulator is the Regie de l'energie du Quebec, created in 1996 by the Loi sur la Regie de l'energie. For some disputes you may also want to involve the Protecteur du citoyen (Quebec Ombudsman, for procedural fairness questions about a municipal body) or the Commission d'acces a l'information (for data and access-to-information issues).

The escalation ladder
1
Talk to Hydro-Sherbrooke customer service

Most issues resolve here. Call 819-821-5400 or use the city online portal.

2
Ask for a written city-level review

If the front line can't fix it, request a written decision from the Hydro-Sherbrooke management office. This creates the paper trail needed for the next step.

3
File a complaint with the Regie

The Regie de l'energie accepts customer complaints once you've exhausted Hydro-Sherbrooke's internal process. Free, written submission via the Regie complaint form.

4
Protecteur du citoyen or court

Last resort. The Protecteur du citoyen can review procedural fairness. The Cour du Quebec (Small Claims division for amounts under $15,000) is the standard court route for residential damage disputes.

Selectra energy expert answers

Can I choose a different electricity supplier than Hydro-Sherbrooke?

Not for the energy commodity. If your address is inside the City of Sherbrooke, Hydro-Sherbrooke is your distributor and your retailer by municipal mandate. Quebec has no licensed competitive electricity retailers for residential customers either way: even outside Sherbrooke, the alternative is Hydro-Quebec (the Crown utility) or one of the other eight municipal utilities and the Rouville rural cooperative. The only way to be served by Hydro-Quebec is to live outside the boundaries of the City of Sherbrooke.

I have a power outage. Who do I call?

Always Hydro-Sherbrooke, not Hydro-Quebec. Call the 24/7 line at 819-821-5400 or check the outage map on the city website. For a downed live wire or any life-threatening situation, dial 911 first and stay back at least 10 metres. If you call Hydro-Quebec by mistake, the operator will redirect you to Hydro-Sherbrooke, but it costs you minutes.

Why is Sherbrooke served by a municipal utility instead of Hydro-Quebec?

Historical. The City of Sherbrooke founded its own electricity service in 1908, long before the first nationalisation wave of 1944. When Hydro-Quebec absorbed the remaining private utilities in 1963, nine municipal services already in operation were allowed to stay independent and Hydro-Sherbrooke is one of the largest of them. The municipal service buys bulk power from Hydro-Quebec at the wholesale L tariff, runs its own substations and distribution wires inside the city limits, and resells the energy at rates approved by the Regie de l'energie du Quebec.

Does Hydro-Sherbrooke pay compensation if my food spoils during an outage?

Not automatically. Quebec has no statutory automatic compensation regime for outages, unlike the UK's Ofgem Guaranteed Standards. You can file a damage claim with Hydro-Sherbrooke under its Conditions de service, but claims are evaluated case-by-case on negligence and are routinely denied if the outage was caused by weather (treated as force majeure), wildlife, third-party contact or planned work. Keep dated receipts and photos. Most home insurance policies cover food spoilage and surge damage at a low deductible and are usually a faster route.

How are Hydro-Sherbrooke rates set?

Hydro-Sherbrooke files a rate proposal with the Regie de l'energie, just like Hydro-Quebec does. In practice the residential tariff tracks the Hydro-Quebec Rate D structure very closely: a small daily fixed charge plus a two-tier inclining block (about 7.8 ¢/kWh on the first 40 kWh per day, about 10 ¢/kWh above that). The bulk supply that Hydro-Sherbrooke buys from Hydro-Quebec moves at the wholesale L tariff, which is the main reason municipal-utility rates in Quebec are aligned with Hydro-Quebec retail rates.

Who do I call for a new connection or service upgrade?

Hydro-Sherbrooke. The municipal service handles all wiring on poles and pads inside the city limits, the meter and the connection. Call 819-821-5400 or apply through sherbrooke.ca. You will typically need a municipal building permit, a Regie du batiment du Quebec (RBQ) electrical permit pulled by a licensed master electrician, and a load calculation.